What is the activity variance along the critical path?

What is the activity variance along the critical path?

3.11

Dave Fletcher (see Problem 3.10) was able to determine
the activity times for constructing his laser scanning
machine. Fletcher would like to determine ES, EF, LS, LF, and
slack for each activity. The total project completion time and
the critical path should also be determined. Here are the activity
times:

ACTIVITY TIME (WEEKS) ACTIVITY TIME (WEEKS) (letter is activity and number is time)

A6 E 4
B 7 F 6
C 3 G 10
D 2 H 7

3.17

Bill Fennema, president of Fennema Hospitality, has

developed the tasks, durations, and predecessor relationships in

the following table for building new motels. Draw the AON network

and answer the questions that follow.

Activity predecessor optimistic Most pessimistic

likely OPTIMISTIC

MOST

LIKELY PESSIMISTIC

A — 4 8 10

B A 2 8 24

C A 8 12 16

D A 4 6 10

E B 1 2 3

F E,C 6 8 20

G E, C 2 3 4

H F 2 2 2

I F 6 6 6

J D,G,H 4 6 12

K I,J 2 2 3

c) Based on the calculation of estimated times, what is the critical

path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before

week 36?

to be completed in excel on seperate pages

Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Writers Hero only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Writers Hero are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Writers Hero is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Writers hero, we have put in place a team of experts who answer to all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.